Project Progress

Deliverables

Code of the associated action

Status

D1 The WEISS website on-line

Action 1

English website available

Dutch pages available

GIS Portal available

March 2010

October 2010

May 2013

D2 An implemented corporate style

Action 1

Finalised

September 2010

D 3 Workshop with potential local end-users and stakeholders

Action 2

Finalised

June 2010

D 4 Workshop information package

Action 2

Finalised

June 2010

D 5 WEISS requirement document version 1

Action 2

Finalised

September 2010

D 6 EU workshop with potential end-users and stakeholders

Action 3

Finalised

March 2011

D 7 Workshop information package

Action 3

Finalised

March 2011

D 8 WEISS requirement document version 2

Action 3

Finalised

March 2011

D 9 WEISS Product Specification document

Action 4

Finalised

April 2011

D 10 WEISS Architecture and Design document

Action 5

Finalised

March 2012

D 11 Prototype iteration 1

Action 6

Finalised

December 2011

D 12  Prototype iteration 2

Action 6

Finalised

March 2012

D 13  Prototype iteration 3

Action 6

Finalised

February 2013

D 14 Analysis results for priority substances in UWWTP

Action 7

Finalised

June 2011

D 15 Source specific emission quantification reports

Action 7

Finalised

July 2013

D 16 Prototype level 1 application & validation reports

Action 8

Finalised

March 2012

D 17 Prototype level 2 application & validation reports

Action 8

Finalised

June 2012

D 18 Prototype level 3 application & validation reports

Action 8

Finalised

February 2013

D 19 Technical documentation

Action 9

Finalised

Reports can be found in the documents section

D 20 Training material package

Action 9

Finalised

Reports can be found in the documents section

D 21 Final seminar

Action 9

Finalised

May 2013

D 22 Cd rom

Action 10

Distributed as USB

 January 2014

D 23 Leaflets on the project

Action 10

Finalised

September 2010 

December 2013

D 24 After Life communication plan

Action 10

Finalised

 December 2013

D 25 Laymans report

Action 10

Finalised

 December 2013

D 26 Notice board

Action 10

Finalised

December 2012

D 27 Newsletters

Action 10

Finalised

May 2011December 2011, November 2014

D 28 Press relaese

Action 10

Finalised

 Jaarverslag Water 2012

D 29 Records of the meetings of the Steering group

Action 12

Not realised

 

D 30 Records of the meetings of the Project board

Action 12

Finalised

Reports can be found in the documents section

D 31 Records of the meetings of the Advisory board

Action 12

Finalised

Reports can be found in the documents section

D 32 Quarterly monitoring reports

Action 12

Completed

 Reports can be found in the documents section